Company | Projects | Complaints | Judgement/Orders |
Parsvnath Developers | Parsvnath Privilege, Greater Noida | Flat booked by buyers in 2007, possession delayed | To repay Rs 47.5 lakhs, along with interest of 18% per annum. |
Parsvnath Exotica, Ghaziabad | Delay in completion of project | Refund of entire amount paid by buyer, with interest of 12% per annum. | |
Jaypee Group | Kalypso Court project, Noida Expressway | Delay in possession | Penalty of interest at 12% per annum; Directed to hand over possession to buyer by 21st July, 2016, failing which, the builder has to pay a penalty of Rs 5,000 per day, per flat, till the project is completed. |
Amrapali Group | Liesure Park Greater Noida | Delay in completion of project | The court will enforce the undertaking furnished by the Group of arranging 87.28 crore to complete the project |
Unitech | Aspen Green project at SAS Nagar, Mohali | Possession of plot (booked in December 2011) not given within the committed date | Refund of Rs 3.04 crore, along with 18% interest per annum. |
Lodha Group and Shree Sainath Enterprises | Lodha Luxuria, Thane; Fairfield building | Apartment not delivered, and sold to third party; Non-execution of agreement to sell | Refund of the entire amount with 18% interest thereof and compensation of Rs 1 lakh. |
Lok Housing & Construction Ltd | Mumbai based SRA project | Failure to start construction since 2014 | To pay monthly payment of 4.3 lakh to three home buyers till the possession is given |