- Greater Noida:A deeper analysis of the construction activity scenario in Greater Noida reveals some glaring issues. Developers in Greater Noida were expected to deliver around 84,200 units in 2017, of which only 13% were delivered and an additional 39,000 units (46%) are committed for completion by 2018 year-end. Due to the National Green Tribunal (NGT) directive, projects in Greater Noida have been stalled for years due to land litigations between farmers and the developers.
- Ghaziabad:Of the 29,300 units which were to be delivered in 2017, nearly 86% failed to meet their deadline. Only 14% have been handed over to buyers, and around 8,100 units (32%) are envisaged to be completed by year-end 2018. While a few projects have been sealed for recovering the Ghaziabad Development Authority’s (GDA’s) development charges, others face difficulties in obtaining completion certificates.
- Gurgaon: The Millennium City was also not able to deliver around 19,400 units in 2017; the delivery of these units was shifted to future dates. Out of 27,300 units committed for delivery in 2017, only 29% were handed over to buyers and around 14,400 units (53%) are being pushed for completion by year-end 2018. The good news is that most of the delayed units are likely to be completed in 2018, and the delivery of only limited units is being pushed to the subsequent years.
- Noida: Barring of construction activity within a 10-km radius from Okhla Bird Sanctuary between 2013-15 has stalled a large number of projects in Noida region. Out of the 23,900 units committed for delivery in 2017, 67% were unable to meet the deadline. Around 7,900 units (49%) of the delayed units are projected to be completed by December 2018.